Network planners selecting a load break switch inside an RMU must separate normal load switching duty from fault-making and fuse/breaker protection roles before comparing outdoor cable-ring quotations.
This load break switch guide focuses on practical procurement and layout controls for the package below. Pair the checklist with the approved single-line for load-break-switch-rmu-selection-guide — não substitui a aprovação da empresa de serviços públicos ou de um consultor.

A load break switch is sized for switching load current under defined conditions — it is not automatically a short-circuit interrupter. Ring schemes often combine load break ways with fuse-switch or circuit-breaker functions on transformer feeders.
Write the functional role of each way on the single-line so vendors cannot substitute a look-alike cubicle with the wrong duty class.
Leitura relacionada: ring main unit RMU selection guide e outdoor ring main unit cable entry planning.
| Selection input | Network risk if vague | Proprietário |
|---|---|---|
| Rated voltage / insulation | Wrong clearance class | Network SLD |
| Load break current rating | Unsafe switching duty | Operating study |
| Short-time / fault-making rating | Cubicle damage on faults | Estudo de faltas |
| Number of ring / tee ways | Wrong enclosure footprint | Feeder plan |
| Cable type and entry direction | Civil trench rework | Cable design |
| SF6 / alternative gas notes | Handling & environmental compliance | HSE / ops |
| Motorization / remote control | SCADA interface gap | Automation team |

Importante: For load break switch, freeze these inputs on a controlled revision before normalizing commercial bids; late changes cascade into civil, protection, and factory drawings — align with prática das normas IEC e as notas da fonte da autoridade do projeto.
Outdoor RMUs need gland plates and bending radii that match MV cable specs. Grounding continuity between tank, cable screens, and the earthing grid should be verified before backfill.
If SF6 is used, retain handling, leak-check, and end-of-life recovery notes in the O&M pack — treat them as controlled environmental documents.
| Item | Propósito | Enviar com citação |
|---|---|---|
| Way function matrix (LBS / fuse / CB) | Duty clarity | Yes — locked |
| Rated currents and fault duties | Network match | Yes — study refs |
| Cable entry GA and gland schedule | Civil interface | Yes — before PO |
| Gas type and handling procedure | HSE compliance | Yes — with O&M |
| Interlock and earthing notes | Safe operation | Yes — ops sign-off |
| Routine test certificates | Factory evidence | Yes — FAT list |
| Remote / motor option datasheet | SCADA integration | If specified |
Anexe esta tabela a cada revisão do pedido de cotação (RFQ) para que os fornecedores devolvam propostas técnicas comparáveis em vez de extractos de catálogo.
Verify mechanical operation of each load break way, earthing switch position indications, and cable sheath bonds. Record gas pressure (where applicable) against the nameplate band.
Do not close onto a live ring until protection on tee-offs is proven and the operating sequence is filed with the control room.
For many load break switch scopes, begin engineering review with Shenheng Power’s SF6 gas insulated ring main unit (RMU) entrada de catálogo documentada na página do produto.

Limites de aplicação: Para load break switch (load-break-switch-rmu-selection-guide), trate a página de catálogo ligada apenas como um ponto de partida de engenharia. não congelar load break switch aquisição quando o estudo de defeitos do projeto, a desclassificação por altitude ou o tipo de aprovação da concessionária excedem as classificações publicadas nessa página do produto.
If the load break switch study points to a different scheme or rating for load-break-switch-rmu-selection-guide, browse the página de categoria e enviar os contributos para o estudo Contactar a Shenheng Power.
Load break covers defined load-current switching; fault-making and interrupting duties require ratings proven for short-circuit conditions.
Freeze ring and tee ways on a function matrix tied to the network plan before requesting enclosure GA drawings.
When compact outdoor footprints and proven gas-insulated modules fit the site — still subject to local environmental handling rules.
Short-time withstand and any fault-making claims must match prospective fault levels at the installation point.
Gland plate size, entry direction, and bending radius mismatches with trenches or ducts.
Leak-check procedures, recovery requirements, and O&M references should travel with the equipment dossier.